The short answer
Yes, a homeowner who commissions roof work counts as a domestic client under CDM 2015, but the duties are not left with you. Regulation 7(1) places them on the contractor, or on a principal contractor when a second firm joins the project, and the project needs a construction phase plan.
Are you a domestic client?
HSE defines the term in plain words: "A domestic client is any individual who has construction work carried out on their home, or the home of a family member, that is not done as part of any business." If you own a house and hire a roofer to repair or replace the covering, you fall inside that sentence. If the roof belongs to a landlord's business or a company, you do not, and the ordinary client rules apply.
The label sounds heavy, but the idea underneath it is simple. A client commissions the job, and the Regulations list what a client must see to for the work to run safely. A homeowner has not got the knowledge of a developer, a school or a retailer, so the law moves that burden to the people running the site.
The label matters for one practical reason: it tells you whose job it is to think about safety on your project, and the answer is the firm you hire rather than you. It also explains why a roofer may talk to you about access, the scaffold and where materials will be stored before any work begins, even for a small job.
Where the duties go under regulation 7(1)
Regulation 7(1) of CDM 2015 says the domestic client's duties "must be carried out by" one of three parties, depending on how the project is set up.
| Situation | Who carries the duties |
|---|---|
| A single contractor on site | That contractor |
| Several contractors on site | The principal contractor |
| A written agreement naming a principal designer | The principal designer |
A re-roof by a single roofing firm falls in the first row. Bring in a second trade, perhaps a separate scaffolding firm or an electrician for a roof window, and a second contractor is on the project, so the second row applies and someone must act as principal contractor. A homeowner does not need to learn the duties by heart, but should know they exist and who holds them. Ask who that is when you book, and note the answer. The answer is useful if work goes wrong, since it names the firm that answers for how the site was run, and it tells you who to write to.
What the plan is for
Regulation 15(5) says "the contractor must draw up a construction phase plan, or make arrangements for a construction phase plan to be drawn up". Where a principal contractor is appointed, regulation 12(1) says "the principal contractor must draw up a construction phase plan". Either way the project has a plan, whatever its size and however small the roof.
A plan for a roof job deals with what makes roof work risky: working at height, protection for people and property below, where the scaffold stands and who may enter the working area. On a small repair the plan can be short, and on a full re-roof it will run longer. It is a working document, so it can be updated as the job develops.
You can ask the firm you are hiring how it deals with those points. A contractor who answers plainly about access, edge protection and the people passing underneath is taking the duty seriously. Our guide on scaffolding for roof work explains the highway licence for a scaffold over a footway, and we arrange the licence with our scaffolder.
What it means when you hire a roofer
In practice the Regulations should not add paperwork to your week. The point of regulation 7(1) is that the duties settle on whoever is running the job. You still choose the firm, agree the work and pay the bill, and the rest of your position as a consumer is covered in your rights when you hire a roofer.
At Total Roofing Great Yarmouth the survey covers the whole roof, and a written quote follows, carrying one total price. If a quote leaves you unsure about access or safety, ask before you sign. Our guide on how to read a roofing quote lists what a written quote should state, and that is a fair place to start the conversation about the plan and about who is running the site.
Keep the quote and any correspondence about how the work will be managed, because they are clear evidence of what was agreed if a question comes up later.