A terraced roof is joined to its neighbours at the party walls, so a re-roof touches shared structure as well as your own tiles. This guide covers party wall notices, the scaffold licence, planning, Building Regulations and matching next door.

Get a written quote

Call 01493 277103WhatsApp us

Thick moss on the concrete tiles of a chalet bungalow's north-facing slope

What a terrace changes about a re-roof

A detached house has a roof that is its own. A terraced house does not: its slopes run up to a wall that it shares with the house on either side, and the covering, the flashing and sometimes the chimney stack are all tied into that line. A new roof therefore finishes against structure that belongs partly to someone else.

Three things follow from that. The legal side is the Party Wall etc. Act 1996, which can apply to work at the shared wall and sets its own notice periods, separate from planning. The practical side is access, because scaffold has to stand on a street, on a pavement or at the rear. And the visual side is next door, because the two roofs sit next to each other and a change in covering shows at the join.

None of these stops a terraced house being re-roofed, and a house in the middle of a row has the most shared structure to deal with. They add steps that a detached house can skip, and they are far easier to deal with before the work starts than after the old covering has come off. The sections below take them in the order they arise.

For the wider job, see our roof replacement page, and the guide to the re-roofing process for the sequence of work.

Flashings and chimney breasts at the party wall

The Party Wall etc. Act 1996 lists the work a building owner may do to a party wall, subject to serving notice. Two items on that list matter on a roof. Section 2(2)(g) covers cutting away from a party wall any footing or any projecting chimney breast, jamb or flue. Section 2(2)(j) covers cutting into the wall of an adjoining owner's building in order to insert a flashing or other weather-proofing.

The second is the one that can apply to a terraced re-roof. A new lead or other flashing can be chased into the brickwork where the roof meets the neighbour's wall or stack, and cutting that groove into the adjoining owner's wall is party structure work. A roofer who only replaces the covering on your side, leaving the old flashing where it is, may not need to cut at all, so what the roof requires is settled at the survey.

Removing a chimney breast always needs Building Regulations approval, whether or not the wall is shared. A breast on the party wall brings the Act in as well, since cutting one away is on the s2(2)(g) list, so it is not a decision for one owner alone.

Roof work at a party wall and the notice that goes with it
WorkSectionNotice
Cutting in a flashing2(2)(j)At least two months
Cutting away a chimney breast2(2)(g)At least two months
New wall on the boundary1(2)At least one month
Excavation nearby6(5)At least one month

Myth

A flashing is just part of my roof, so the neighbour has no say.

Fact

Cutting into the adjoining owner's wall for a flashing is party structure work, with a notice.

Serving notice, and what the neighbour can do

Notice is the building owner's job. For party structure work it has to go out at least two months before the date on which the proposed work will begin, describing what is planned and when. Where the work is excavation close to a neighbour's foundations or a new wall on the boundary, notice is at least one month ahead, not two. Party wall questions go to a party wall surveyor, not to building control.

The neighbour has three options. They can consent in writing, in which case the works may start with the consent in writing of the adjoining owners and of the adjoining occupiers. They can dissent. Or they can do nothing: if no consent is given within the period of fourteen days, that silence counts as dissent, and the law treats a dispute as having arisen. Silence is not agreement, and GOV.UK says so directly: you cannot assume that no response means they agree to the works.

Dissenting is not the same as vetoing. The matter then goes to the section 10 surveyor procedure, where an agreed surveyor or one for each side settles how the work is done. A surveyor is therefore appointed only if there is dissent from the neighbour or no reply within 14 days. The fourteen days is a reply period, not the lead time, and an earlier start can be agreed in writing by the neighbour.

In a terrace a house has a neighbour on each side, and the notice goes to each adjoining owner whose wall is affected. A tenant or landlord next door complicates it, because an earlier start needs written consent from the occupiers next door as well as the owners. If the house next door is empty or the owner cannot be found, that needs resolving early. Keep a copy of every notice served.

How a party structure notice runs

  1. Written notice is served on the adjoining owner by the building owner.
  2. Notice goes out two months or more before work begins.
  3. The neighbour consents in writing, or does not reply.
  4. No consent within 14 days counts as dissent.
  5. Dissent sends the matter into the section 10 surveyor procedure.
  6. Work starts when the notice period has run or consent is given.

Scaffold on the street and the licence it needs

Where a terraced house has no side access, scaffold goes up across the front. Before scaffolding goes over a footway or carriageway, a licence is required from the county council as highway authority, issued under section 169 of the Highways Act 1980, and never by the district or borough council. Scaffold on the front of a terrace obstructs the footway, which is what section 169 addresses.

That law says no person shall erect or retain on or over a highway any scaffolding or other structure which obstructs the highway without a licence. We arrange the licence with our scaffolder. The licence is separate from planning and from the party wall notice, and none of the three stands in for another.

Scaffold at the back of the house is a different matter. A rear yard or garden is not highway, so no highway licence is needed, but a neighbour's access or a shared passage is still a practical question. Where scaffold would stand on or lean over land that is not yours, ask the owner before the day it goes up.

A trunk road is the exception to the county route: the licence for a trunk road comes from National Highways, on 0300 123 5000, and that applies only to the trunk road itself.

Matching next door, and what planning says

Re-roofing a house is normally permitted development under Class C. That covers a terraced house, so a new covering of any kind can go on without an application provided the Class C conditions are met and no Article 4 direction, listing or flat applies. Nothing in Class C requires you to match the neighbour. The Class C conditions limit how far new work can stand proud of the old slope (0.15 metres) and stop any alteration rising above the highest part of the original roof, so a new covering with a deep build-up is measured against those two limits.

Matching is still worth thinking about, because the join between two roofs is the one place a neighbour's eye goes, and a covering that differs sharply from next door's is visible from the street. A terrace is read as a row, and a roof in a different colour or texture stands out at the join. If next door has recently re-roofed, ask what went on, and whether the neighbours would consider a shared decision on the covering and the ridge. It is a courtesy and not a legal duty.

If you want to add a dormer, the rules for a terrace are tighter. Class B sets "40 cubic metres in the case of a terrace house" and "50 cubic metres in any other case", and it does not apply at all on article 2(3) land: a conservation area, the Broads or a National Landscape. Our guide to re-roofing in a conservation area goes through the designations.

An Article 4 direction removes named permitted development rights within the area it covers, so a terrace inside a conservation area is worth asking about. Check with the council whether an Article 4 direction applies. A flat in a converted terrace has no householder rights, so the council is asked first. Planning belongs to the council, or to the Broads Authority inside its executive area.

Building Regulations, the survey and the written price

By the Planning Portal's test, no Building Regulations application is normally needed if less than 25 per cent of the total "building envelope" is affected and less than 50 per cent of the roof is affected, and a complete re-cover reaches over half the roof, outside that test. Building control is carried out by the council's building control team or by a registered building control approver.

Approval is also needed when a new covering material is 15 per cent or more heavier than the old covering, and in a terrace the load runs into the party walls, so weight deserves a proper check. Our guide on changing to a heavier roof covering explains the test.

Where one contractor does the job, CDM 2015 makes that contractor responsible for a homeowner's client duties, and where several are on site the principal contractor takes them over. Every project carries a written construction phase plan, which the contractor makes. The survey before quoting takes in the shared ridge, the stack and the party wall abutments, and it is followed by a single written total. If the roof needs more than the slope you rang about, the findings are put in plain words.

A photograph of the roof from the street and from the loft can be sent on WhatsApp first, and it helps to say whether next door's roof is attached to yours at the ridge.

Questions and answers

Must the neighbour be told before a terraced re-roof starts?

Only where the work falls within the Party Wall etc. Act 1996, for example chasing a flashing into the adjoining owner's wall, or cutting away a chimney breast on the party wall. The notice is written, comes from you as building owner and goes out at least two months before the date on which the proposed work will begin. Telling the neighbours about the scaffold is a courtesy, not a legal step.

Can my neighbour stop me re-roofing?

Not by dissenting. A neighbour who dissents, or who does not reply within 14 days, starts the surveyor procedure under section 10 of the Act, where a surveyor sets how the work is done. The roof on your own side is your decision, subject to the planning and Building Regulations checks above, and the notice only affects work to the shared structure.

Who arranges scaffolding permission for the street side?

We arrange it with our scaffolder. Under section 169 of the Highways Act 1980 the county council licenses scaffold across a footway or carriageway. That licence is a separate document from planning and from any party wall notice, and it applies only to scaffold on the highway, so a rear yard does not need one.

Does my new roof have to match next door?

No rule requires it. Class C allows a house to be re-roofed without an application in the normal case, and it does not ask for a match. A listing, an Article 4 direction or a conservation area can add conditions, so check with the council. Owners still weigh up the join, since a terrace is read as a single row.