Three published sources and their different answers
A published figure is not a quote for your roof, but three UK sources give a feel for the range. Each says what it measured, they do not agree with one another, and all three come with their dates. None of it is Total Roofing's own pricing.
Which? Trusted Traders put replacing the whole roof of an average three-bedroom house at £7,000 to £21,000 excluding VAT, in a survey of 11 traders gathered in November 2025. Its prices include labour and materials. HomeBuilding's page, last updated on 30 September 2025, works from a standard semi with three bedrooms, a 65m2 roof and plain concrete tiles, which may cost between £10,000 and £15,000; the cost of a Welsh slate roof for the same property might reach £18,000.
On MyJobQuote's page of 3 November 2026 the average new roof costs around £5,250, and its slate page of 6 October 2026 gives the average cost of fitting a slate roof as around £7,800. It states no VAT basis for either figure. The three sources cover different houses and use different methods, and no reason for the gap between them is given, so treat each as a marker rather than a target.
A written quote outside all of these ranges is not wrong for that reason alone. Where a figure sits depends on the house and on the work chosen. Large roofs, awkward access and heavy coverings push a price up, and a small simple roof can fall below the bottom of the range. What matters is that the quote names the work it covers, which the later sections come back to.
Whole-roof figures from three sources
| Which? whole roof | £7,000 to £21,000, average three-bedroom house |
|---|---|
| HomeBuilding three-bed semi, plain concrete tiles | £10,000 to £15,000 |
| HomeBuilding Welsh slate, same house | might reach £18,000 |
| MyJobQuote UK new roof | average around £5,250 |
| MyJobQuote slate roof | average around £7,800 |
Which? Trusted Traders, November 2025, excluding VAT, survey of 11 traders. HomeBuilding, last updated 30 September 2025. MyJobQuote, pages dated 3 November 2026 and 6 October 2026, no VAT basis stated.
What moves the price on your own house
Six things set one house apart from the next, and the survey can measure every one of them. The first is size: the area of the roof, counted in plan across every slope, sets how much covering, batten and underlay the job needs. The second is the shape. A hipped roof, a dormer, a chimney, a valley or a bay each adds cutting and flashing, so two houses with the same floor area can price differently.
The third is the covering you choose, which gets its own section. The fourth is access: how the roof is reached, whether scaffold must stand on the pavement or road, and how the old material comes down and goes away. The fifth is what lies under the old covering, meaning the battens, the underlay, the rafters and the fascia boards. The sixth is waste, including whether any of the old material needs special handling, since a roof stripped of its covering produces a large volume to remove.
To a smaller degree, the work around the roof counts too. Lead flashings at the chimney and walls, ridge and verge fittings, roof windows, ventilation and gutters can each be renewed with the roof or left alone, and the choice changes the total. A roof renewed to current insulation standards carries the cost of that upgrade as well.
All of it ends in one written total. What you can do is ask what that price rests on: which covering, which parts are being renewed, and what the quote says about the roof's insulation and ventilation.
What the survey measures before pricing
- Roof area across every slope
- Shape: hips, valleys, dormers and chimneys
- How the roof is reached from outside
- The covering, battens and underlay now in place
- Rafters and fascia boards that can be seen
- Any old material needing special handling
The covering: price, weight and expected life
The covering is the biggest single choice, and it shows in the figures above: HomeBuilding's own plain concrete tile example and its Welsh slate example for the same house differ by thousands of pounds. A covering also has a lifespan, which is part of its real cost over the years. The table gives the approximate lifespans HomeBuilding lists.
| Covering | Approximate life | Source and note |
|---|---|---|
| Welsh slate | 100+ years | HomeBuilding |
| Spanish natural slate | 75-100 years | HomeBuilding |
| Clay tile | 60-80 years | HomeBuilding |
| Plain concrete tile | 40-50 years | HomeBuilding |
Marley gives a different view of tiles: "Typically, roof tiles are expected to last for around 60 years", and it adds that "This is not a guarantee or warranty of its longevity." HomeBuilding's plain concrete range of 40-50 years sits below that general figure. A lifespan shows what a covering can do when it is installed and looked after, and it makes no promise about your own roof.
Pitch limits the choice as well. Cupa says BS 5534 puts the minimum pitch for natural slate at 20 degrees, for moderate exposure with a 500mm slate and a 115mm overlap, and Sandtoft's data sheet gives its clay Old English Pantile a minimum pitch of 30 degrees with a 75 mm headlap. A covering has to suit the pitch the roof already has, or the structure itself has to change.
Weight raises its own question. A new covering that is 15 per cent or more heavier than the old one needs Building Regulations approval, and a structural engineer or surveyor should look at the roof first. Which products weigh more turns on the products chosen, so this guide names no material. Our guide on Building Regulations for re-roofing covers the weight test and the rest of the rules.
Scaffold, old timbers and waste
A whole new roof calls for safe working at height around the full perimeter, so scaffold belongs to the job. Where the scaffold would stand on the public footway or carriageway, a highway licence comes from the county council, and we arrange the licence with our scaffolder; the scaffold sits within the written quote.
The old covering is stripped to reveal the battens, the underlay and, at the eaves and ridge, the rafters and boards. A timber that has rotted or been attacked is cut out and replaced, and that is the part of a quote nobody can fully price from outside. Ask any firm, ourselves included, how a timber problem found once the covering is off would be dealt with, and get the answer in writing before you sign.
Waste matters because of what the old roof is made from. HSE's guidance is: "If the building was built or refurbished before 2000, assume that there is asbestos in it." Careful removal of whole asbestos cement sheets is non-licensed work, and sheeting that is broken or badly damaged falls into a separate, notifiable category. HSE's instruction is "Use a lockable skip for asbestos", and the household consignment-note exemption is for hazardous waste "other than asbestos waste". MyJobQuote puts the UK average for taking asbestos off a roof at around £2,750 (page dated 9 September 2026).
That figure shows how far a roof can move from the ranges above when an old material needs specialist handling. It also means a roof on a building built or refurbished before 2000 is worth testing ahead of accepting any quote, since a result changes the plan and the price together. Our guide on what a re-roof involves follows the work from scaffold to sign-off.
Myth
The lowest total on a quote means the lowest-priced roof.
Fact
A low total can leave out parts of the roof that another quote includes, so compare what each names.
Insulation, Building Regulations and the grants that do exist
Re-roofing is also an energy question. Where more than 50% of a roof's surface is renovated, Approved Document L brings in the upgrade of the entire element, if feasible. Table 4.3 sets the improved figure at 0.16 W/(m²·K), against a threshold of 0.35. Where the full upgrade is not feasible or would not pay back within 15 years, the roof is upgraded as far as is feasible within that payback. The insulation is part of the roof price, so it is worth asking about when you compare quotes.
On tax and support: HMRC's Notice 708/6 covers insulation in roofs or lofts, zero-rated for supplies "made between 1 May 2023 and 31 March 2027", after which the reduced rate of 5% applies. That relief is for energy-saving materials, not for a roof covering or for repairs. Funding the government runs in England goes to insulation, loft insulation among it, and to heating upgrades, not to roof replacement; the GOV.UK pages list what is available.
If your household income is usually £36,000 a year or less and your home is privately owned with an EPC of D to G, you may be eligible for the Warm Homes: Local Grant, which can include loft insulation. The Energy Company Obligation is closing on 31 December 2026, so check GOV.UK or your council soon should you think you qualify. Nothing here lowers a roofing quote.
Comparing quotes and signing with care
Quotes for one roof can sit far apart with neither being unreasonable, since they may price different jobs. With another firm's quote in hand, check what it covers: the covering named, the underlay, the battens, the ridge and verge fittings, the flashings, the gutters and the removal of the old material, and what it says about scaffold and VAT. A total that leaves half the roof out is only cheap on paper.
Look for a quote that names the work, shows a single total and says what happens if a timber problem is found. Be wary of pressure to decide on the spot or to pay a large sum up front. Our post on telling a cowboy roofer from a good one goes through the warning signs.
Your own rights matter at this stage. Sign at home after a survey and you have 14 days to cancel. Work can begin sooner only on a written request, and making one leaves the right in place, though what has already been done may still be owed. The Citizens Advice consumer helpline on 0808 223 1133 can advise, and our guide to signs you need a new roof helps you judge whether replacement is warranted.