Which Lead Code for Flashings?

Lead is sold by code, a number from 3 to 8. For flashings the choice sits between code 4 and code 5, and Leadworx's table shows which job each code is listed against.

Get a written quote

Call 01493 277103WhatsApp us

A lead-lined parapet gutter at the foot of a slate roof

The short answer

Code 4 for general flashing work, and code 5 where the flashing is vertical or on a pitch. Leadworx, a lead flashing maker, says code 4 has become the standard choice for general flashing work and lists code 5 for general, vertical and pitched use. Soakers sit at code 3.

Reading the code numbers

A lead code is a grade of rolled sheet. Leadworx says the grades run from 3 to 8, that they are set by the Lead Sheet Training Academy (LSTA), and that they comply with BS EN 12588. A bigger number means a thicker, heavier sheet, and the table below shows how far each step goes.

Weights differ between suppliers, so the figures are Leadworx's own. They show the step between codes and are not a universal table. Codes 3 to 6 are shown because they are the ones that matter for flashing work.

Lead codes as Leadworx lists them
CodeThicknessWeightUse against it
31.32 mm14.97 kg/m²Soakers, light duty
41.80 mm20.41 kg/m²Light duty, general
52.24 mm25.40 kg/m²General, vertical, pitched
62.65 mm30.10 kg/m²Large roofs

Codes 7 and 8 are listed as heavy duty and fall outside everyday flashing work. Our guide to lead codes explained sets out the whole table and the thinking behind it.

Code 4 and code 5 for flashings

Leadworx writes that "Code 4 has become the standard choice for general flashing work". That is a maker describing the trade, not a rule, and nothing obliges anyone to use code 4 for any flashing. It is still a sensible yardstick to hold a quote up against.

Aprons, cover flashings and stepped pieces against a wall or chimney fall within the general work that sentence describes. Code 4 can be shaped by hand around tile profiles and brick courses, and it is light enough to be carried by its clips without sagging at a short run.

Code 5 sits one step up at 2.24 mm against 1.80 mm in Leadworx's figures, and Leadworx lists it for general work on vertical faces and pitches. A tall flashing running up a wall, or a piece with a long run, gains from the added stiffness, because a larger area of thinner sheet moves more and droops under its own weight. Whether a particular detail needs it is a call made at the roof, with the wall, the covering and the exposure in front of you. Neither code is a promise of a longer life, and the next section explains why a code alone settles less than it seems to.

Soakers, and why they drop to code 3

A soaker is a small folded piece of lead, bent into an L shape, laid beneath each course of tiles or slates beside a wall or chimney side. One arm lies under the covering and the other turns up the brickwork. Leadworx lists code 3 against soakers and light duty.

Soakers sit under the covering rather than out in the weather, and they have to be bent tightly and repeatedly into the same shape. The lighter sheet takes that fold easily. Our page on lead soakers shows how they work with the stepped flashing over them.

This is why one roof can carry three codes at once: soakers at code 3, the stepped flashing over them at code 4, and a cover flashing against a tall wall at code 5, each matched to the duty of that piece. A quote that says only the word lead has left out the one fact a comparison needs.

Getting the code written down

The specification names the grade for each detail, which settles what is going on your roof. A quote worth comparing therefore gives a code against each flashing, so that two quotes can be read side by side and a difference in price can be traced to a difference in sheet.

Three questions cover it. What code is each piece, and why that one? Are the soakers lighter than the aprons, as Leadworx's table would suggest? And is each piece cut to a length that lets it move with the temperature, since a thicker code does not cure a piece that is too long or fixed too tightly?

On our survey, the lead at each junction is judged on its own terms: the wall it meets, the covering in front of it and how exposed it stands. You receive one written total price when the survey is done. The lead roofing and leadwork hub lists the other lead jobs, and the guide to lead flashing cost covers the cost side of lead work.

If a quote names no code at all, that is worth asking about before anything is agreed, because the thickness of the sheet changes both the price and how the flashing behaves as it ages.

Questions and answers

Is code 4 lead required by law for flashings?

No. The code 4 sentence is Leadworx's description of the trade: it says code 4 has become the standard choice for general flashing work. Your roof's specification sets the code for each detail, and a different code can be right where the detail calls for it, such as code 5 for a tall wall.

Is thicker lead always the better flashing?

No. A heavier code is stiffer, harder to shape into a tight joint and heavier on its fixings, so it adds cost without adding much to a small flashing. A thick sheet that is cut too long, or fixed too tightly, can still split as it moves with the weather.

Can I tell the lead code by looking at a flashing?

Not reliably. Thickness is hard to judge once lead is dressed and fixed, and the edge may be buried in a joint in the wall. The code is read from the specification or the quote. If neither names it, ask for it to be written down before work begins on site.