Over-Cladding an Asbestos Cement Roof

Over-cladding fits a new sheet roof over an old asbestos cement one instead of taking the old sheets away. This guide sets the overlay beside removal, using HSE's rules on fragile sheets and non-licensed work, and says what to settle first.

Get a written quote

Call 01493 277103WhatsApp us

Rear flat roofs of a brick shop parade with flats above

Why an asbestos cement roof is over-clad

Asbestos cement was used for roof sheeting on factories, farms, garages, schools and warehouses, and some of those roofs are still in place. The sheets are bound with cement, so while they are sound and left alone they release little. The trouble comes when they are weathered, cracked, drilled, broken or walked on. At that point the owner has a roof that leaks and a material that should not be disturbed.

Over-cladding answers that problem in one way. A new covering is fixed above the old sheets, so the old roof stays in place beneath it and serves as a deck. The building is closed in by the new sheet roof and the old one is never lifted off. The work goes on over the top, without taking the old sheets down or breaking them up.

That does not make it the right answer for every building. The alternative is to strip the old sheets and fix new ones in their place, which removes the material. The two routes differ in cost, in time, in what is left behind and in who has to do the work. This guide puts them next to each other. Our commercial roofing hub has the surrounding guides.

The first step on either route is to be sure what the sheet is, and a vague answer is a reason to stop and test. HSE advises assuming that any building built or refurbished before 2000 contains asbestos. A sample taken and tested by a specialist settles it. Without that, the owner is guessing, and a wrong guess is more costly on a roof than almost anywhere else.

What HSE says about the sheets

HSE divides asbestos work into three groups, placed according to the material and its condition. Asbestos cement roof sheeting falls in the first group, non-licensed, as long as it is handled and lifted carefully and never broken up. HSE counts sheets that have weathered but are otherwise sound in that same group. Sheeting that is badly damaged or in pieces, through fire or flooding for example, moves into the second group, notifiable non-licensed work. In the third group, most work on asbestos insulating board is licensed, and HSE lists "AIB white soffit panels to underside of roof eaves" among the places it is found.

Non-licensed does not mean unregulated. It means the work needs no licence from HSE, yet the people doing it still have to control exposure to the dust. The three groups are a matter of law, and the owner and the contractor each carry duties. The question for an owner is which group the job falls into and who is equipped for it.

HSE guidance A14 says plainly that "AC roofs are always fragile". Asbestos cement sheets become brittle with age, and a person who steps on one can fall through. That applies to anyone on the old roof during the work, because an overlay is built above sheets that cannot take weight. Our guide to fragile roof safety explains the access methods that go with that.

How HSE groups the work

  • Sound or weathered asbestos cement sheet, carefully handled: non-licensed
  • Substantially damaged or broken up sheet: notifiable non-licensed
  • Most asbestos insulating board work: licensed
  • Soffit panels under the eaves may be insulating board
  • Treat any pre-2000 roof as containing asbestos

How an overlay is built

An overlay is not simply a new sheet laid on the old. The new covering has to be carried by something, and it has to be fixed to something, and neither can be the brittle asbestos cement. In one form of the work, support brackets or rails are fixed down through the old sheets to the purlins beneath, and the new sheets are fixed to those. Insulation can go in the space between.

That fixing step is where the risk sits. Each fixing that passes through an old sheet is a hole made in asbestos cement, which is the activity HSE guidance treats with caution. How the holes are made, what controls apply and who is doing it are the questions to settle before the first screw. A roof that is overclad without a plan for the fixings has simply moved the problem.

The new roof must also be designed for the loads it will carry, and the frame beneath has to be able to take them. The purlins carry the old sheets already. Adding brackets, a new set of sheets and insulation adds weight, so the structure is checked as part of the survey. A frame that has corroded or lost its fixings is a reason to rethink, not to proceed.

Finally, the details have to work. Ridge, verges, eaves, gutters, rooflights and flues all have to be formed above the old roof in a way that sheds water, and old gutters and fixtures that stay in place may need extending. The survey looks at each one before a price is given.

An overlay in outline

  1. Confirm what the old sheets are and what condition they are in
  2. Check the frame and purlins for the extra load
  3. Plan access that does not rely on the old sheets
  4. Fix supports through to the purlins, with the controls in place
  5. Fit the insulation and new sheets, then the trims

What an overlay leaves behind

The asbestos is still there. That is the main trade-off and it should be said without hedging. An over-clad roof has a new surface, and under it sits the old asbestos cement, with its fixings and its fragility. It is sealed away from view and from weather, not removed.

The consequences are practical. Anyone who later cuts into the roof, adds a rooflight or a flue, or strips it back has to know the old sheets are there. For a non-domestic building the owner's duty to manage asbestos continues, and the location should be written down where the next person will see it. The building keeps an asbestos item for good, and the cost of dealing with it is deferred, not removed.

A leak through the new roof lands on the old one. If water gets into the space between the two roofs, it can sit there unseen. That is a reason to take the details at the penetrations and trims seriously and to inspect the new roof as part of a plan. Our guide to commercial roof surveys explains how a roof is examined over time.

On the other side of the ledger, an overlay avoids breaking, lifting and bagging old sheets. It keeps the building weathertight during the work and it avoids the cost of removal and disposal. For some buildings that is the sound decision, and for others the better route is to take the material out. The choice rests on the condition of the sheets, the frame, the future of the building and what the owner is prepared to carry.

Removal and the waste afterwards

Removal means taking the old sheets off the building and sending them for disposal. Sheets that come off whole and are handled with care sit in HSE's non-licensed group. Whether a given roof belongs there depends on its condition, because a sheet that has broken moves the job into notifiable work.

The waste has its own rules. HSE's EM9 says: "Use a lockable skip for asbestos", and it adds that a standard skip with sheeting thrown over it is not good enough. For households, the consignment note exemption covers domestic hazardous waste "other than asbestos waste", so asbestos is outside it. A roof on a commercial building is not a household, so the carrier and the consignment paperwork have to be right, and both are worth the owner checking.

Where the waste may be taken depends on the county. In Norfolk, Norfolk County Council says: "We do not accept any type of asbestos at any of our recycling centres, even during our hazardous waste events." In Suffolk, the county council says you cannot take it to any Suffolk Recycling Centre, and its contractor collects small amounts of household cement bonded asbestos for a fee. A commercial roof is not household waste, so the route is a carrier registered for the job.

MyJobQuote gives a UK average of around £2,750 for taking asbestos off a roof, from its page last updated 09/09/26, and around £325 for an asbestos survey in 2026. They are national averages for a household roof, not a price for any particular building, and a commercial roof is priced once it has been surveyed.

Choosing between overlay and removal

Four things decide the route. The first is the condition of the sheets: sound sheets suit an overlay, and badly broken ones raise the stakes whichever way you go. The second is the frame, since the overlay adds weight to the structure. The third is the future of the building. A building due for demolition or conversion will have to deal with the asbestos then, and an overlay moves that cost to the next stage. The fourth is the practical situation: whether people and stock must stay in the building and whether the roof can be closed to access.

CDM 2015 applies to the work. A business roof is not a domestic client's home, so the building owner has client duties of their own, and every project has a construction phase plan. Our guide to CDM on commercial roof work covers the duties. The planning and Building Regulations route for a re-covering is checked with the council's building control team before work starts.

Whichever way you go, ask the same questions of anyone offering to do the work. What do they believe the sheets are, and what have they checked? What will they do about the fixings? Where will the waste go, and who carries it? Who holds the duties under CDM? A firm that cannot answer these before the work starts is not ready to start it, and a written answer is better than a spoken one that nobody can check later.

We survey the roof before quoting, look over all of it and report anything else we find. The price that follows is one written total for the work agreed, and where the survey raises a question about the material, you are told so plainly.

Questions and answers

Is over-cladding an asbestos roof legal?

Fitting a new roof over an old asbestos cement one is a route owners choose, but the fixings that pass through the old sheets disturb the material, so the controls that HSE sets out apply. Check the Building Regulations route with the council's building control team before work starts, and confirm in writing who carries the duties under CDM.

Does over-cladding remove the asbestos?

No. The old asbestos cement sheets stay in place beneath the new roof. They are covered, not taken away, and the building owner's duty to manage asbestos continues for as long as they remain in the building. Anyone who later cuts into the roof or strips it back has to know that the old sheets are there.

Can I take asbestos cement sheets to the tip?

Not at a household recycling centre. Norfolk County Council turns away every type of asbestos at its recycling centres, and Suffolk County Council says you cannot take it to any Suffolk Recycling Centre. Waste from a commercial roof goes with a registered carrier, in a lockable skip, never in an open one.

Is a licence needed to remove asbestos cement roof sheets?

Sound asbestos cement sheeting that comes off whole falls in HSE's non-licensed group. Badly damaged sheets are notifiable, and work on asbestos insulating board falls in the licensed group. Which group your roof belongs to depends on its condition, so that is settled before anyone picks a method, and it is not a matter for guesswork.