What industrial roof cladding is
Cladding is a covering made of large sheets or panels fixed to a frame, instead of small tiles laid in courses on timber. On an industrial roof the frame is a set of purlins, which are the horizontal rails that span between the main steel or concrete portals. The sheets are fixed to the purlins, run from eaves to ridge and are lapped so that water passes down off each sheet onto the one below.
A building owner will meet three systems. The first is single-skin profiled sheet: one layer of profiled metal or fibre-cement sheet, with insulation and a liner added or not. The second is a built-up system, where a liner sheet, a layer of insulation, spacers and an outer sheet are assembled on the roof in that order. The third is the composite panel, a factory-made sandwich with an outer face, an insulation core and an inner face in one unit.
Each system fails in its own way, so the first job on any cladded roof is to find out which one it is. A single-skin sheet leaks at a lap or a fixing. A built-up system can hold water between its layers. A composite panel leaks at a joint or a cut and may be damaged in a way that cannot be seen from the surface. Knowing the type tells the surveyor where to look.
Our commercial roofing hub explains the other roofs a business may own. This guide stays with cladding, and with the sheets and panels that cover industrial units.
Profiled steel sheet: profile, laps and falls
Profiled metal sheet is formed with ribs and troughs, which give it strength across its span and let it carry water down the slope. The profile matters because it sets how far the sheet can span between purlins, how the laps are made and where the fixings go. Two sheets with a similar look can have different rules, so a replacement sheet has to match the profile of the roof it joins, or the whole run has to be changed.
Water is shed along the troughs, so the pitch has to be enough for it to run off and not to back up under the laps. A sheet manufacturer publishes a minimum pitch for each profile, and that figure belongs to the product data, not to a general rule. A roof that has been laid below the minimum for its profile, or that has sagged into a hollow, holds water at the laps and leaks there.
End laps, where a sheet runs over the one below it up the slope, and side laps, where neighbouring sheets overlap across the roof, are sealed with a strip of sealant sandwiched between the layers. Over time that sealant hardens, shrinks and loses contact. Re-sealing a lap from the outside is a repair that works for a while but does not change the cause, so the survey asks whether the lap is failing because of the sealant, the fixing, the pitch or movement in the sheet.
Steel sheeting carries its protection in a coating on the surface. When the coating is scratched, worn through or cut, the steel beneath is exposed. A surveyor looks at the colour and the surface of the sheets, at the ridge and eaves where debris collects, and at any place where one metal touches another, because contact between different metals can set up corrosion.
Insulated composite panels
A composite panel is made in a factory, so the thickness of its insulation core, the finish on each face and the joint between neighbouring panels are all set before it reaches the site. That consistency is its attraction. It also means that panels have to be ordered to size, handled with care and joined in the way the maker specifies. A dented panel, a crushed edge or a damaged joint cannot be fixed by adding more sealant.
The weak point is the joint, because the panel itself is a closed unit. Joints between panels, the ridge, the verge and the eaves all depend on the maker's detail: the right trims, the right sealant and the right fixings, each in the right place. On an older roof the sealant and the trims are the first things to look at, along with any fixing that has worked loose.
Water that gets into the core is a particular problem, because the core cannot be seen. A panel may look sound from the outside and still be wet inside. A moisture reading, a sample from an edge or a cut-back at a joint is the way to find out, and the surveyor should say plainly when the condition of a core is not known.
Fire performance is a separate question. Insulation cores are made from different materials and are assessed differently for how they behave in a fire. If a roof is being recovered or replaced with panels, the choice of core is a Building Regulations matter, and building control is asked before the order is placed.
Terms on a cladded roof
- PurlinHorizontal rail that carries the roof sheets
- LinerInner sheet under the insulation in a built-up roof
- LapWhere one sheet overlaps the next
- FlashingMetal trim that seals a junction
- Composite panelFactory-made sheet with an insulation core
Fixings, sealants and cut edges
A fixing holds a sheet to a purlin and also makes a hole in the sheet. Each one carries a washer that seals the hole, and each washer is a small part with a limited life. When the washer cracks, the fixing leaks and water follows the shank through the sheet. A visible fixing that is loose, missing, over-driven or standing proud of the sheet is a defect to record, and a field of fixings that show rust is a finding in its own right.
Where the sheets sit on the purlins, and how many fixings each one gets, are set by the manufacturer's fixing pattern for that profile. A pattern gives the position and the number, and the number depends on the position of the sheet on the roof. Following it is part of keeping the roof in place in strong wind. Substituting the wrong screw or leaving some out because the sheet seems tight is the kind of shortcut that shows up after a gale.
Cut edges are a second weak point. Wherever a sheet is cut on site, for a rooflight, a flue, an upstand or a ridge trim, the protective coating is cut as well. The bare edge is exposed to water, and corrosion starts there and spreads inward under the coating. The remedy is to treat the cut edge, to cut with the right tool and to avoid leaving swarf on the surface, because swarf rusts and stains. Our guide to the over-cladding of an asbestos cement roof returns to fixings, because they matter more when the sheet beneath is brittle.
Sealants are a repair aid and are not a cure. A bead of sealant on a defective washer or a split lap buys time. It does not repair a fixing that is loose, a sheet that is cracked or a trim that is at the wrong angle, and the survey looks for which of these is the real cause.
Rooflights, gutters and the details that leak
A cladded roof is a large area of simple repeating sheeting, so the faults cluster at the exceptions: rooflights, ridge and verge trims, valley and parapet gutters, flues, plant bases and the junction where the roof meets a wall. A survey spends its longest time at these places.
Rooflights are sheets of translucent material set into the line of the cladding. Their laps, their fixings and the material itself all age, and a sheet that has become brittle may not support a person's weight. Treat any rooflight as fragile until it has been checked, and do not step on one. Our guide to fragile roof safety sets out why that matters.
Gutters on an industrial roof are a different kind from the ones on a house. Box gutters, parapet gutters and valley gutters carry water from more than one slope and have to stay clear and sealed. A joint that has opened or an outlet that has blocked puts water onto the wall or into the building. The fall that Brett Martin gives for guttering, "1mm for every 600mm" towards the outlet, applies to the gutter itself whatever the building is.
The wall junction is a place where a trim, a flashing or a sealed joint is the only barrier. Where the roof abuts a taller wall, water running down the wall lands on the cladding at the junction, and the detail there has to cope with it. A cracked sealant joint or a lifted flashing is something the survey looks for, and it is a repair that can be done without recovering the roof.
Repairing, recovering or replacing: what to settle first
Three questions come before any decision to repair or replace a cladded roof. What are the existing sheets made of? What condition is the frame in? What do Building Regulations require? Each can change the plan.
The first is the sheets. HSE's advice to owners is to presume asbestos in any building built or refurbished before 2000. A cladded roof that may be fibre-cement or asbestos cement is a different job from one in steel, and no work should start until that is settled. Our guide on over-cladding an asbestos cement roof covers that case.
The second is the frame. New sheeting is fixed to the purlins, and a purlin that has corroded, bent or lost its fixings to the portal will not hold a fixing. A roof recovered over a weak frame holds the same defects under a new surface. The survey covers what can be seen of the frame, both from the roof and from within the building.
The third is the regulatory route. Recovering or replacing the sheets can bring Building Regulations into play, and the energy rules for a commercial building sit in a different approved document to the one covering dwellings, so the household figures do not apply. We check the route with the council's building control team, or a registered building control approver, before work starts. Planning may also matter, and a planning route is checked with the council as well. Cost is set by the area, the system, the access and the frame's condition, and we price it after a survey. The survey is followed by one written total price.
Settle before work starts
- What the existing sheets are made of
- The condition of purlins and their fixings
- The Building Regulations route for the new covering
- Access and edge protection for everyone on the roof
- Whether the system is single skin, built up or panel