The short answer
Removing the doors ends the exemption unless a wall, door or window takes their place. Approved Document L paragraph 0.14 makes a separating wall, door or window a condition of the exemption, and the home's heating must not extend into the conservatory. Check with building control before the opening is made.
Why the doors matter to the regulations
For England, a conservatory at ground level and up to 30 m² is exempt from the energy rules only while a wall, door or window still separates it from the house and the home's heating is not extended into it. The doors or wall are what make it a separate space. Take them away and the conservatory is simply a larger room opening off the house, and it is judged as one.
The wording is in Approved Document L, paragraph 0.14. Its condition (d) says that any wall, door or window that separates the extension from the dwelling has been retained or, if removed, has been replaced with a wall, door or window. Condition (e) adds that the heating system of the dwelling is not extended into the conservatory or porch.
Both conditions have to hold, along with the other three: ground level, a floor area not over 30 m² and glazing that meets Part K. Remove the separation and the exemption is gone, whatever the size of the room. Our explanation of the 30m² conservatory rule sets out all five.
What changes when the exemption ends
The energy rules then apply to the conservatory as a new part of the home. In practice the glazing, the walls, the floor and the roof of the former conservatory are looked at against the standards for new work, and the roof is the part we are asked about. Table 4.2 of Approved Document L sets 0.15 W/m²K for a roof and 2.2 W/m²K for a rooflight, with its own roof window figure.
That has a direct bearing on a roof that was installed as a glazed conservatory roof. A polycarbonate or glass roof, fitted when the conservatory was exempt, will not meet a figure of 0.15, and the council may ask what the plan for the roof is. A solid insulated roof is one answer, and the cost and the structure come into the decision.
A new roof must comply with building regulations whether or not the room is exempt. What the exemption changes is the standard that the rest of the room has to meet.
Changes that end the exemption
- Taking out the doors or wall to the house
- Running the home's heating into the room
- Enlarging it beyond 30 m²
- Glazing that fails the Part K test
The practical steps
Before the opening is made, ask building control whether the plan needs approval and what standard the room will be held to. For Great Yarmouth Borough Council and East Suffolk Council addresses, check with their building control teams. The wall you remove may carry the floor above or the roof, so a structural check and the right support over the new opening belong at the start.
Read the roof, too. If the conservatory has a glazed roof, decide at the same time whether to leave it or replace it, because doing both in one project is easier than returning to the roof later. If you replace it with a solid roof, the Planning Portal says planning could be needed if the roof's make-up or appearance alters in a big way, so the council is asked about that too.
Our page on conservatory roof building regulations covers what building control looks for, and our guide on whether a conservatory can take a solid roof covers the frame.
Where the roof comes in
The doors are not a roofing job, and the wall, the opening and the heating belong with building control and a structural engineer or surveyor. The roof is where Total Roofing Great Yarmouth comes in. The roof gets a full survey from us, and anything else we noticed is reported in plain words before one written total is quoted for the roof work.
If you are planning to open the house into the conservatory, send a photo of the roof from outside on WhatsApp, 07880 284133, and we can look at the roof before the other work is settled. That way the roof decision is made with the full plan in view, not after the wall is open and the room is in use. Settling the roof first also means the finishes inside, such as flooring and decoration, are chosen once and not disturbed by later roof work. If the survey shows the old roof is near the end of its life, you will know that before the ceiling is lined or the furniture is moved in.