The short answer
The covering and the frame between them set the pace, so no single duration is fair to quote. A panel swap is the smallest job and a solid, insulated roof the largest, with the survey, the council check and any scaffold licence all coming before work begins. The written price follows the survey.
Why one number would mislead you
Replacing the polycarbonate sheets on a sound frame is one kind of job. Stripping a glazed roof and building a solid, insulated, tiled one is another. The second involves rafters, a ridge, insulation, a ceiling and the finishing around them, so comparing the two on length is like comparing a puncture repair with a new engine.
Weather is a further reason not to promise a figure. A conservatory frame with its roof off is open to the sky, and it is covered or closed in as the work moves along. Rain, wind and what turns up beneath the old covering all affect how the work runs, and none can be known from the ground.
What can be said is the order in which things happen, and where each stage can take longer. That is more useful than a number, because you can ask any firm about each stage and compare the answers.
The stages, in order
The sequence below covers a full replacement. A panel swap skips some stages and compresses others, but the first stage never changes: no price is set before someone has been up and looked at the roof itself.
- Survey: the whole roof and the frame under it are looked over, and the route with building control is checked where the new roof is solid.
- Scaffold, where the job needs it: a licence for the pavement or road comes from the county council, and we arrange the licence with our scaffolder.
- Strip: the old sheets or glazing units, caps and seals come off the roof.
- Frame checks: the exposed frame and the top beam are checked, along with the fixing to the house wall.
- Build-up: the new sheets, or the rafters, insulation, battens and covering, go on.
- Finishing: flashings at the wall, ridge, gutters and any ceiling or lantern complete the roof.
Each stage hands over to the next, so a delay at one is felt at all the later ones. That is the main reason to ask about the order of work and not only the finish date.
What stretches each stage
The survey and the council check come first, and they depend on other people. For a solid roof, the Planning Portal says that every new roof has to meet building regulations, and adds: "If the change significantly alters the structure or appearance of the roof, then planning permission may be required." Waiting for those answers is outside any roofer's control, which is why we ask the council before work starts.
Frame checks can change the plan. If the top beam has rotted, a corner joint has opened or the base under a dwarf wall has moved, the frame is put right before a heavier roof goes on. That is the stage where the findings can add work. Our page on whether a conservatory can take a solid roof explains what the structure is checked for.
Access matters too. A conservatory with a narrow side passage or a first-floor window above it asks for more care in moving materials.
The finishing stage depends on the covering. Flashings at the house wall, the ridge and the gutters are all part of what makes the room weathertight, so they are done as part of the roof and not left until later.
Getting a programme you can hold someone to
Because the stages lean on one another, ask for the order of work and who is responsible for each stage, then ask for the programme in writing. A firm that names the stages but cannot say which ones apply to your roof has told you very little.
At conservatory roofs we survey the roof as a whole before quoting, and we point out anything extra we find. The written quote is one total price. If the survey turns up something that changes the job, you are told before any work is booked, and you decide what happens next.
Two questions are worth putting to anyone you ask: what happens to the room between the strip and the new roof going on, and what is the plan if the frame needs work that was not visible at the survey. Written answers to both make a quote far easier to compare with another firm's.
If cost is the other question, our replacement cost page gives published ranges with their dates, and the two questions go together because a larger job costs more and takes longer. Neither can be fixed until the roof has been surveyed.