What does building control ask of an Ellingham re-roof?
The short answer
A whole re-roof takes in more than 50 per cent of the roof, so it goes to building control. A heavier covering needs a structural check as well.
Two limits from the Planning Portal apply. No building regulations application is normally needed where "Less than 25 per cent of the total 'building envelope'" is affected and "Less than 50 per cent of the roof is affected". A whole re-roof passes the second line the moment the old covering comes off, so it is a building control matter whatever goes back on, and CNC Building Control is the body for Ellingham addresses.
Weight is the second trigger. Approval is needed for a covering that comes out "15 per cent or more" heavier against what was there before, and the Planning Portal advises that a structural engineer or surveyor be consulted. For that reason the rafters, purlins and wall plates are examined from inside the loft before any new tile or slate is priced, since a frame built for a light covering may need work before a heavier one goes on.
The body for Ellingham addresses is CNC Building Control, set up as a partnership of five councils (South Norfolk, Norwich City, Broadland, King's Lynn & West Norfolk and Fenland) and its Norwich office can be rung on 0808 168 5041. Instead of the council team, a registered approver can be used. Planning permission is a separate matter, and South Norfolk Council decides it for Ellingham, so an Ellingham owner has two different contacts for two different questions, and neither answers for the other.
What the survey reads on an Ellingham re-roof
- Tiles or slates: cracks, slips and open joints
- Ridge and verges: bedding and fixings
- Lead at chimneys and wall abutments
- Timbers and underlay, seen from the loft side
- Rainwater goods and where they discharge