Can a Sprowston chimney breast come out, and who gets notice?
The short answer
Approval under the Building Regulations is always required, and a shared wall brings a party wall notice to the neighbour.
The Planning Portal states the structural side bluntly: Removing a chimney breast always needs Building Regulations approval, and the Portal's reason is that a breast belongs to the structure. For a Sprowston address the application goes to CNC Building Control, a partnership of five councils (South Norfolk, Norwich City, Broadland, King's Lynn & West Norfolk and Fenland); to reach its Norwich office, call 0808 168 5041. A registered building control approver is the other route.
A shared wall adds a second duty. Under the Party Wall etc. Act 1996 the building owner serves the notice, and a party structure notice must be served "at least two months before the date on which the proposed work will begin". Removing a breast that projects from a party wall is one of the works the Act names. If the neighbour has not consented "within the period of fourteen days", the Act treats that silence as dissent, and the surveyor procedure takes over.
Questions on a party wall go to a party wall surveyor, not to building control, and the notice is the owner's to serve. From the loft we can say what the stack above the room will need, because removing a breast can leave the stack, and the roof timbers above, short of support. The chimney repairs page covers the stack itself.
Order for a breast on a party wall
- Building control application to CNC or an approver
- Owner serves the party wall notice, at least two months ahead
- Neighbour consents, or the 14 days pass
- A surveyor steps in if the neighbour dissents