Does a full re-roof in Halvergate need a building regulations application?
The short answer
Yes, since stripping the whole roof passes the 50 per cent limit. A small repair can stay under both Planning Portal limits and need none.
The Planning Portal's test has two limits and both must hold. No building regulations application is normally needed where "Less than 25 per cent of the total 'building envelope'" is affected and "Less than 50 per cent of the roof is affected". Stripping a whole Halvergate roof uses up the second limit by itself, so a full re-roof is a building control matter whatever the covering.
Building control here is CNC Building Control, a partnership of five councils (South Norfolk, Norwich City, Broadland, King's Lynn & West Norfolk and Fenland), run for this part of Norfolk from its Norwich office on 0808 168 5041. A registered building control approver is the other route. CNC's guide to warm roofs says "No ventilation is required for these types of roofs" and of a cold roof that "Ventilation is required for these roofs", so the loft side of the survey establishes which kind you have.
Weight is the second trigger. A new covering that "increases the weight of the roof covering by 15 per cent or more" needs approval, and the Planning Portal's advice is to take a structural engineer's or surveyor's view before work begins. The survey therefore reads the rafters, purlins and wall plates from inside the loft as well as the slopes outside. Our roof replacement page covers whole-roof jobs and roof repairs the smaller ones.
What the survey reads before a Halvergate re-roof
- Rafters, purlins and wall plates, from inside the loft
- Battens and underlay beneath the old tiles or slates
- Eaves courses, where rain leaves the roof
- Valley linings and the lead at chimney stacks
- Verge edges and ridge bedding along the top
- Gutter runs and downpipes at the foot of each slope